DTL-PRJ0072-MTH-001 · Construction Methodology · Rev 0
Prepared for
Shark Bay Resources Pty Ltd
Useless Loop · Heirisson Prong · Shark Bay, Western Australia
Project
Bitterns Recycling — Field Piping Installation
CONSTRUCTION METHODOLOGY

General & Technical Method Including
The Thermal Dynamics Plan

Document numberDTL-PRJ0072-MTH-001
Revision0 — Issued for Approval
Date16 July 2026
AttentionMr John Stephens — Principal's Representative
Contract · Purchase orderSBS10627 · PO 182113
Scope of work23092-SOW-024rD
Pipelines560-BR-301-P1 · 355-SW-302-P1
Submitted underSOW Section 4.6 — Project Execution Plan, prior to Site mobilisation
DTL (WA) Pty Ltd  ·  2/28 Horus Bend, Bibra Lake WA 6163  ·  ABN 45 677 646 454  ·  Commercial-in-Confidence
DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 1 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

Document control

Document numberDTL-PRJ0072-MTH-001
Document titleConstruction Methodology — Bitterns Recycling Field Piping Installation
ProjectDTL-PRJ0072 · Bitterns Recycling Project
ClientShark Bay Resources Pty Ltd (SBR)
StatusIssued for Approval

Revision history

RevDateDescriptionOriginatedCheckedApproved
016 Jul 2026Issued for Approval — Bitterns Recycling field piping installation, SOW 23092-SOW-024rD

Approval

This methodology is submitted for the approval of the SBR Representative in accordance with SOW Section 4.1 and Section 4.6, prior to mobilisation to Site.

PREPARED AND APPROVED — DTL (WA) PTY LTD
Name / position
Signature
Date
APPROVED — SHARK BAY RESOURCES PTY LTD
Name / position
Signature
Date
DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 2 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

Contents

1Introduction 2Reference documents 3Definitions and acronyms 4Project description and battery limits 5Site conditions 6Organisation and responsibilities 7Sequence of works 8Mobilisation and site establishment 9Materials handling, storage and stringing 10Jointing — butt fusion 11Thermal dynamics management 12Above-ground installation and restraint 13Underground road crossings 14Tie-ins, valves, drains and instruments 15Testing and inspection 16Quality and manufacturer's data report 17Environment, health and safety 18Environmental management 19Traffic management 20Site restoration and demobilisation AAppendix A — Pipeline section schedule BAppendix B — Thermal design basis summary
DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 3 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

1Introduction

This document describes how DTL (WA) Pty Ltd (DTL, the Contractor) will execute the field piping installation for the Bitterns Recycling Project at Shark Bay Resources' Useless Loop solar salt operation.

It is submitted to the SBR Representative under SOW Section 4.6 as the methodology component of the Project Execution Plan, and incorporates the detailed plan for managing the thermal dynamics of the pipeline required by SOW Section 4.1. It is issued for approval prior to mobilisation to Site.

1.1 Purpose

The document is prepared so that:

1.2 Scope of this document

This methodology covers the installation of pipeline 560-BR-301-P1 from the F7 bitterns pump station to pond PM1, and the seawater flush supply pipeline 355-SW-302-P1, between the battery limits stated in Section 4. It excludes the items listed at SOW Section 5, which remain outside DTL's scope.

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 4 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

2Reference documents

DocumentTitle
23092-SOW-024rDBitterns Recycling Project — Field Piping Install Scope of Work
SBS10627DTL Pipeline Construction Contract (Supply & Install), as adjusted by Annexure 1
PO 182113Shark Bay Resources purchase order
00-SPE-P-010SBR Piping specification
00-SPE-Q-001SBR Construction Quality Control procedure
00-SPE-C-002SBR Roadworks Construction specification
00-SPE-G-002Useless Loop — Information for Contractors
SBR-PRO-0082SBR Contractor Management Procedure
23092-KMZ-001rBPipeline route, access, laydown and turnaround constraints (Google Earth)
560-BR-301-P1Bitterns recycling pipeline — F7 to PM1
355-SW-302-P1Seawater flush supply pipeline
AS/NZS 4130Polyethylene pipes for pressure applications
AS/NZS 4131Polyethylene compounds for pressure pipes and fittings
AS/NZS 2566.1Buried flexible pipelines — structural design
POP003PIPA — Polyethylene pipe butt fusion jointing
AS 1170.2Structural design actions — wind actions (Region C)
DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 5 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

3Definitions and acronyms

TermMeaning
ARVAir release valve
CoCCertificate of conformity
DLPDefects liability period
EH&SEnvironment, health and safety
HDPEHigh density polyethylene
HVHigh voltage
ITPInspection and test plan
JHAJob hazard analysis
MDRManufacturer's data report
NATANational Association of Testing Authorities
PE100Polyethylene compound, MRS 10 MPa
PQRProcedure qualification record
SBRShark Bay Resources Pty Ltd
SDRStandard dimension ratio
SOWScope of work
SWISafe work instruction
WPSWelding procedure specification
DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 6 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

4Project description and battery limits

SBR operates a 7,000 hectare solar salt field at Useless Loop on Heirisson Prong, approximately 900km north of Perth. Bitterns — the concentrated brine remaining after the majority of the NaCl has precipitated in the crystalliser ponds — is currently collected in the F5 and F7 ponds, where it infiltrates the aquifer below the pond basement. To reduce reliance on that seepage process and recover the remaining NaCl, the bitterns will be pumped from F7 to the first pond in the evaporative process (PM1) and recycled.

4.1 The works

Bitterns recycling pipeline560-BR-301-P1 — approximately 20,700m of DN560 co-extruded white HDPE, F7 bitterns pump station to pond PM1, across 13 sections (Appendix A)
Seawater flush pipeline355-SW-302-P1 — approximately 750m of DN355, teed from the existing seawater transfer arrangement
Underground crossingsCrossings 2–10 by DTL. Crossing 1 (Upper and Lower Bar Road) coordinated and completed by SBR
Drain pointsChainages 2810 and 8060, position and orientation as directed by the SBR Representative
Flow metersThree free-issued DN350 meters at chainages 8030, 13886 and 20200, with reducers and expanders to suit
Actuated valveOne free-issued DN350 actuated valve near the pipeline discharge
Air and vacuum releaseARV and vacuum breaker offtakes along the route, as fabricated items

4.2 Battery limits

The battery limits of this scope are the first flange connection after the bitterns pump station (15-PP-102 pump discharge flange) and the discharge flange into the PM1 pond. Piping at the new pump location and outside these limits is excluded (SOW Section 5).

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 7 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

4.3 Principal-supplied materials

The following are free issued by SBR (SOW Section 6). DTL offloads, receives, inspects, records and stores these materials, and reports any transit damage or shortfall to the SBR Representative on receipt.

MaterialQuantity
DN560 PE100 PN10 / SDR17, 21m lengths3,276 m
DN560 PE100 PN8 / SDR21, 21m lengths3,066 m
DN560 PE100 PN6.3 / SDR26, 21m lengths14,784 m
DN355 PE100 PN8 / SDR21, 21m lengths777 m
DN560 PE100 PN12.5 / SDR13.6 sweep bends6 off
DN355 PE100 PN10 / SDR17 sweep bend1 off
DN350 actuated valve, flow meters, manual valving, drain points, air / vacuum release valvesPer drawings
Diesel for mobile plant, light vehicles and generatorsFree issued
DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 8 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

5Site conditions

The ambient conditions below are taken from SOW Section 8 (Bureau of Meteorology averages for Denham) and form the environmental basis of this methodology, including the thermal design at Section 11.

ParameterValueBearing on the method
Highest recorded shade temperature47.0 °CUpper bound of the thermal expansion case
Mean daily maximum temperature26.8 °CTypical working conditions
Mean daily minimum temperature17.8 °CPreferred jointing and tie-in window
Lowest recorded temperature5.5 °CLower bound of the thermal contraction case
Relative humidityup to 100%Fusion face preparation and weld protection
Average yearly rainfall223.2 mmTrench dewatering, access trafficability
Maximum daily rainfall182.4 mmOpen excavation controls at crossings
Maximum operating wind speed23 m/sLifting and stringing limits; AS 1170.2 Wind Region C

DTL is responsible for ensuring plant and components supplied are suitable for these conditions, and allows for all weather throughout the Contract period.

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 9 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

6Organisation and responsibilities

DTL is fully self-sufficient for the construction period. SBR plant (Franna, telehandler, EWP, forklift) and facilities (crib rooms, offices, ablutions) are not relied upon (SOW Section 4.3).

RoleResponsibility
Contractor's Representative
Mr Tyson Knight
Contractual authority for DTL under SBS10627 Schedule 1 Item 3. Point of escalation.
Project ManagerDelivery, programme, resourcing, SBR interface, change and variation management.
Site SupervisorDay-to-day execution and crew direction. Attends the 15-minute SBR daily pre-start, weekly site meetings and any other meeting requested by SBR (SOW Section 7.9). Owns the pre-start and JHA process.
EH&S AdvisorEH&S management system, risk assessment, incident management, statistics for the weekly report.
Quality / QAITPs, weld register and weld mapping, traceability, MDR compilation.
PolyweldersButt fusion jointing to the approved WPS. Only operators qualified for the machine and pipe class weld.
Plant OperatorsExcavation, lifting, stringing, backfill and compaction.

All personnel complete the SBR site induction before commencing work and meet the pre-mobilisation requirements at SOW Section 7.5, including pre-employment medicals, drug and alcohol screening, police clearance and a current tickets and qualifications matrix.

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 10 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

7Sequence of works

  1. Pre-mobilisation — Project Execution Plan approved, including this methodology and the thermal design at Section 11. Bank guarantees lodged, insurances current, statutory declaration provided, risk assessment and traffic management plan issued.
  2. Mobilisation and site establishment — personnel, plant, fuel pod, facilities and laydown established at the locations nominated from the KMZ review. SBR inspection of DTL plant before use.
  3. Survey set-out — route, chainages, crossings, drain points, instrument locations and tie-ins set out and preserved against the supplied drawings.
  4. Materials receipt — free-issued pipe and fittings offloaded, inspected, recorded, stored.
  5. Stringing and jointing — pipe strung along the prepared benches and butt fused into strings.
  6. Underground crossings 2–10 — excavation, sleeving where nominated, laying, backfill and compaction. Timed to suit SBR operations and approved by the SBR Representative.
  7. Section 2 — Upper/Lower Bar crossing — executed within the SBR HV shutdown window. Power to the townsite is isolated; SBR coordinates haul road traffic control.
  8. Above-ground lay, snaking and restraint — strings laid to the corridor with the thermal snaking regime at Section 11, earth pinned at 150m centres.
  9. Tie-ins and appurtenances — ARVs, vacuum breakers, drain points, flow meters and the DN350 actuated valve.
  10. Seawater flush line — 355-SW-302-P1 teed and installed.
  11. Thermal relaxation and final tie-in — pipeline stabilised before closure welds, within the approved temperature window (Section 11.5).
  12. Testing and inspection — to the approved ITPs and 00-SPE-Q-001.
  13. Restoration and demobilisation — areas returned to their previous state to SBR's satisfaction.
  14. MDR — submitted within two weeks of Completion.
DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 11 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

8Mobilisation and site establishment

DTL is responsible for all mobilisation and demobilisation, including transport of personnel, materials and equipment, all transport and other permits, site access for personnel and deliveries, and suitable notice to the SBR Representative before mobilising and demobilising (SOW Section 4.3).

8.1 Laydown and access

The KMZ file 23092-KMZ-001rB has been reviewed to understand access, laydown and turnaround constraints across the full pipeline length. Laydown and facility locations nominated from that review will be confirmed with the SBR Representative before mobilisation. Establishment includes:

8.2 Self-sufficiency and refuelling

DTL will be fully self-sufficient: site office, crib, ablutions, stores, light vehicles and all construction plant. A fuel pod will be mobilised for remote refuelling of diesel plant, vehicles and gensets. Diesel is free issued by SBR and the pod refilled at the SBR workshop fuel tank, on the basis of SBR refuelling the pod once every two days. Refuelling is governed by the Hydrocarbon Controls Procedure (Section 18).

8.3 Survey set-out

DTL will carry out and preserve all survey set-out against the supplied drawings, and is responsible for construction being in the correct positions and to the correct levels. Set-out covers the route centreline and chainages, crossings 2–10, drain points at chainages 2810 and 8060, instrument locations at chainages 8030, 13886 and 20200, and all tie-in points.

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 12 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

9Materials handling, storage and stringing

All pipe is free issued in 21m lengths and is co-extruded white. Handling protects both the pressure wall and the white outer skin — the skin limits solar gain and is integral to the thermal behaviour assumed at Section 11.

ActivityControl
ReceiptEach delivery inspected against the consignment. Certificates of conformity, AS/NZS 4130 compliance certificates and traceability records collected at receipt for the MDR. Transit damage or shortfall reported to the SBR Representative on receipt.
UnloadingNominated unloading points along the route, using slings or padded forks. No chains, hooks or bare steel against the pipe. Exclusion zones for lifting; no personnel under suspended loads.
StorageStacked on level, cleared ground on timber bearers, restrained against rolling, stack heights limited to prevent ovality. Fittings, gaskets and 316SS hardware stored under cover.
StringingStrung along the prepared benches on the nominated side of the corridor. Pipe is not dragged. Ends capped until jointing to keep bores clean.
DamageAny scoring deeper than 10% of wall thickness is cut out. Damaged lengths are quarantined, tagged and reported.
AccessAlong sections 10 and 12, a 4.5m access width to the edge of the pipeline is maintained at all times, including during stringing and laydown.
DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 13 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

10Jointing — butt fusion

Jointing is by butt fusion in accordance with AS/NZS 4130, PIPA POP003 and SBR specification 00-SPE-P-010, to a qualified welding procedure specification approved before production welding begins.

10.1 Method

  1. Machine and operator — hydraulic butt fusion machine sized for DN560, calibrated, with a data logger. Only operators qualified for the machine and pipe class weld. Qualifications are held on Site and included in the MDR.
  2. Preparation — ends cleaned, clamped, aligned and faced to a continuous ribbon. Alignment and ovality checked; toe-in corrected before fusion. Faced surfaces are not touched by hand.
  3. Protection — welding is carried out under a shelter to shield the joint from wind, dust, salt spray and direct sun, and to keep the heat soak even. Welding does not proceed in rain or when wind prevents a stable heat plate temperature.
  4. Fusion — heat plate temperature, bead-up, soak, changeover, fusion and cooling pressures and times to the WPS. Joints are not disturbed until cooling is complete under pressure.
  5. Inspection — every joint visually inspected against the WPS acceptance criteria. Bead symmetry, uniformity and mismatch recorded. Debeading of butt welds is excluded (SOW Section 5).
  6. Traceability — every joint receives a unique number, marked on the pipe and recorded in the weld register against operator, machine, date, time, ambient temperature, pipe heat numbers and the data logger record. Weld mapping gives complete traceability from the MDR back to the joint on the ground.
Ambient temperature is recorded on every joint. It is the reference the thermal design at Section 11 depends on, and is the basis on which final tie-in temperatures are accepted.

10.2 Flanged and mechanical connections

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 14 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

11Thermal dynamics management

"The Contractor shall take into account the likely expansion and/or contraction of pipe materials during construction, after construction, and in operation, so as to ensure that any snaking or contraction of the pipeline is suitably accounted for and does not cause damage to the pipeline and/or its adjacent infrastructure, and remains on/within its intended route/pipe corridors. The Contractor shall propose a detailed methodology which includes the required engineering calculations to ensure this is suitably accounted for, prior to mobilisation to Site, to the SBR Representative's approval." 23092-SOW-024rD, Section 4.1

11.1 The problem

HDPE has a coefficient of linear thermal expansion roughly fifteen times that of steel. A 20.7km surface-laid DN560 pipeline at Useless Loop is exposed to a recorded ambient range of 5.5 °C to 47.0 °C. Left unmanaged, the resulting movement would either displace the pipeline out of its corridor, load adjacent infrastructure, or concentrate stress at the buried-to-surface transitions and at the tie-ins.

The design therefore does not attempt to prevent thermal movement. It accommodates movement along the free-laid lengths and restrains it only where the pipeline must not move.

11.2 Design basis

ParameterValueSource
Coefficient of linear thermal expansion, α0.18 mm/m/°CPE100 material property (typical range 0.15–0.20). To be confirmed against the supplied pipe's manufacturer data.
Highest recorded shade temperature47.0 °CSOW Section 8
Lowest recorded temperature5.5 °CSOW Section 8
Nominal tie-in / restraint reference temperature25.0 °CSelected within the mean daily range (17.8–26.8 °C) to balance the expansion and contraction cases
Design expansion case, ΔTexp22.0 K47.0 − 25.0
Design contraction case, ΔTcon19.5 K25.0 − 5.5
Free length between restraints, L150 mEarth pin spacing, SOW Section 4.3
Pipe outer skinCo-extruded whiteSOW Section 4.1 — limits solar gain and therefore peak wall temperature

The white co-extruded outer skin is not cosmetic. It materially reduces solar absorption and so caps the peak wall temperature above ambient. The skin is protected throughout handling and installation (Section 9) because the thermal case assumed here depends on it.

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 15 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

11.3 Free thermal movement

ΔL = α × L × ΔT
CaseΔTMovement per 150m
Expansion — tie-in at 25 °C to 47 °C22.0 K594 mm
Contraction — tie-in at 25 °C to 5.5 °C19.5 K526 mm

Approximately 594mm of expansion and 526mm of contraction must be accommodated within every 150m of above-ground pipeline. This is the governing number for the method that follows.

11.4 Restrained thrust — why the pipeline is not simply pinned down

If a length were fully restrained against the expansion case, the end thrust would be:

F = E × α × ΔT × Awall

DN560 SDR26 (thinnest wall, longest run): wall t = 21.5 mm, Awall = 36,435 mm², ΔT = 22.0 K

Modulus caseEThrust
Short term (rapid temperature swing)800 MPa≈ 115 kN
Long term (sustained, creep-relaxed)200 MPa≈ 29 kN

Restraining the line against that thrust across 20.7km is neither practical nor desirable. The method below instead lets the pipe move where movement is harmless, and anchors it only at the points where it must not.

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 16 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

11.5 The method

(a) Controlled snaking of above-ground lengths

Above-ground pipe is laid in a deliberate serpentine within the prepared corridor rather than straight. The snake absorbs axial movement as small lateral deflection, so the pipe breathes along its own length instead of pushing at its ends.

A = (λ / π) × √(α · ΔT)

For a serpentine of wavelength λ absorbing thermal strain α·ΔT = 3.96 × 10-3:

Snaking wavelength λRequired amplitude A
30 m≈ 0.60 m
40 m≈ 0.80 m

A snake of approximately 601mm amplitude on a 30m wavelength accommodates the full expansion case within the corridor. Amplitude is set so the pipeline stays within its corridor at all times and, on sections 10 and 12, so the 4.5m access width to the edge of the pipeline is maintained at the snake's widest point — the amplitude is measured from the corridor edge inward, not from the centreline outward.

(b) Restraint regime

LocationTreatment
Above ground, free runningEarth pinned at 150m centres, allowing approximately 2m per earth pin (SOW Section 4.3). Pins guide the line and hold the corridor; they do not act as full anchors.
Within 500m of an ARV or an underground crossingNot earth pinned — the ARV or crossing already constrains the line (SOW Section 4.3).
Buried crossings 2–10Soil restraint and a stable ground temperature effectively fix the pipe. These are the true anchor points.
Buried-to-surface transitionsThe critical detail. Thermal movement from the free length concentrates here. Approach lengths either side of each crossing are laid with additional snaking so movement is absorbed before it reaches the fixed point.
Tie-ins, flanges, valves, flow metersAnchored. Thermal load is not permitted to reach a flange, an instrument or the pump station. Approach lengths are snaked and restrained so the connection sees no axial thermal thrust.
Discharge to PM1 (section 13)Downhill and cross country. Restraint accounts for thermal movement acting with gravity on the grade.
DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 17 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

(c) Installation temperature control

(d) Relaxation before final tie-in

11.6 Verification and hold points

RefHold / witness pointVerification
T1Thermal design approvalThis section approved by the SBR Representative prior to mobilisation (SOW Section 4.1). Hold point.
T2Snake set-out, first 500mAmplitude and wavelength surveyed against Section 11.5(a) and offered for SBR witness before the regime is rolled out across the route.
T3Corridor and access checkSnaked line surveyed against the corridor; 4.5m access confirmed at the widest point on sections 10 and 12.
T4Earth pin installationPin spacing and the 500m ARV/crossing exclusion verified and recorded against chainage.
T5Final tie-in temperatureAmbient at closure recorded against the approved window. Hold point at each anchored tie-in.
T6Post-installation surveyAs-laid position surveyed and issued, establishing the datum against which in-service movement can be checked during the DLP.
The calculations above are the design basis DTL proposes for SBR's approval under SOW Section 4.1. They will be reconciled against the manufacturer's published properties for the free-issued pipe once heat numbers and data sheets are received, and reissued if the confirmed α differs materially from the value adopted here.
DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 18 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

12Above-ground installation and restraint

The majority of the route runs above ground on benches and clearings prepared by others along existing access roads and flow channels. DTL lays the strung and fused pipe into the prepared corridor to the snaking regime at Section 11.5.

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 19 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

13Underground road crossings

DTL constructs crossings 2–10, including all excavation, backfill and compaction. Crossing 1 (Upper and Lower Bar Road) is coordinated and completed by SBR. All underground crossings are direct buried pipe other than crossings 1 and 2, which are sleeved.

13.1 Method

  1. Locate and prove existing services. Ground disturbance permit and SBR authorisation obtained before breaking ground.
  2. Traffic management established to the approved plan (Section 19) before the road is opened.
  3. Excavate to the required depth for approximately 1m of cover, batter or shore to the approved excavation controls, and keep spoil clear of the edge.
  4. Prepare bedding, lower in the pre-fused string or sleeve, and confirm position and level against the set-out.
  5. Backfill in controlled layers and compact to 00-SPE-C-002, restoring the road to at least its previous condition.
  6. Survey and record the as-laid crossing for the MDR.
Programme constraint. Excavation for the underground crossings must be timed to suit SBR's operational requirements. The proposed schedule for the road crossing construction requires the approval of the SBR Representative, and the timing may be changed at SBR's discretion to suit operational needs (SOW Section 10). DTL will not open a road crossing without that approval in place.

13.2 Section 2 — Upper/Lower Bar crossing

Section 2 is the critical interface of the works. SBR trenches and backfills for the sleeved bitterns recycling pipe and the seawater flush line. The pipeline installation must align with the SBR HV shutdown, during which power to the townsite is isolated, and SBR coordinates haul road traffic control. DTL will:

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 20 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

14Tie-ins, valves, drains and instruments

ItemMethod
Drain connection points
Chainages 2810 and 8060
DTL supplies and installs all components excluding the valves. Exact location and orientation as directed by the SBR Representative. Fabricated offtakes — no welded or bolted saddles.
Air and vacuum releaseFabricated offtakes to the drawings. Electro-fusion branch saddles and mechanical tapping saddles are not used. ARVs act as line constraints and are excluded from the 150m pinning regime within 500m (Section 11.5(b)).
Flow meters
Chainages 8030, 13886, 20200
Three free-issued DN350 meters installed for leak detection, with reducers and expanders to suit the DN560 line. Concrete mounting plinths free issued. Anchored — no thermal thrust is permitted to reach the instrument.
Actuated valveFree-issued DN350 actuated valve installed near the pipeline discharge to the drawings, on the free-issued plinth. Anchored as above. Electrical and control connection is excluded (SOW Section 5).
Seawater flush line
355-SW-302-P1
Teed from the existing seawater transfer arrangement to provide flush to the new bitterns pipeline, per the drawings.
IsolationIsolating sleeves and washers at every location where 316SS bolting interfaces with a cast iron valve or instrument body. Stainless is not electrically connected to carbon steel.

15Testing and inspection

All testing is to the relevant regulations, standards, codes, drawings and SBR technical specifications. Where a conflict exists between these documents, DTL will seek clarification from the SBR Representative rather than proceed on an assumption.

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 21 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

16Quality and manufacturer's data report

DTL compiles a Manufacturer's Data Report for the works in accordance with 00-SPE-Q-001 during the works, for submission to SBR within two weeks of Completion. The MDR includes, at a minimum:

Records are compiled progressively rather than reconstructed at the end, so that traceability is continuous and the MDR is deliverable within the two-week window.

17Environment, health and safety

DTL's EH&S Management System specific to this project is submitted as part of the Project Execution Plan (SOW Section 4.6) and includes the Hydrocarbon Controls Procedure and an Emergency Management Procedure.

ElementApplication
Risk assessmentA Construction Risk Assessment Workshop is held before mobilisation. The resulting risk register is issued with the Project Execution Plan (SOW Section 7.6).
Task levelJHAs, safe work instructions and Take 5s for each activity. Reviewed when the task, crew or conditions change — not signed once and filed.
Daily pre-startDTL's supervisor attends the 15-minute SBR daily pre-start. DTL holds its own crew pre-start against the day's JHAs.
InductionsAll personnel complete the SBR site induction before commencing work.
Fitness for workPre-employment medicals, drug and alcohol screening and police clearance for every person, before Site (SOW Section 7.5).
Principal hazardsLifting and suspended loads; excavation and ground disturbance; live plant and traffic interface; HV shutdown at section 2; heat and hydration; remote work and emergency response distance; manual handling of 21m pipe lengths.
ReportingEH&S issues and statistics reported in the weekly report to SBR.
DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 22 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

18Environmental management

19Traffic management

A traffic management plan for the works is issued with the Project Execution Plan (SOW Section 4.6).

20Site restoration and demobilisation

On Completion of the works, and once demobilisation has been approved by SBR, DTL returns all areas used to their previous state. At a minimum, areas are left as they were found, with all rubbish, redundant materials and the like cleaned up and removed, to SBR's satisfaction.

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 23 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

AAppendix A — Pipeline section schedule

Pipeline 560-BR-301-P1, F7 bitterns pump station to pond PM1, per SOW Table 1. The supplied drawings govern; this schedule is the construction sequence reference.

SectionCh. fromCh. to Length (m)DescriptionInstall scope
15-PP-102000Pump discharge flange.Field piping scope battery limit.
Section 1060060015-PP-102 to Lower Bar Rd.First ≈200m above ground, then buried with approx. 1m cover before the bend and for the remainder along the F6/F8 pond levee road. SBR to trench and backfill. Final sleeved crossing in front of the F6/F8 culvert leads into the Lower and Upper Bar Rd crossing.
Section 2600750150Upper/Lower Bar crossing.SBR to trench and backfill, sleeved. Works must align with the SBR HV shutdown — power to the townsite is isolated. SBR coordinates haul road traffic control.
Section 3750975225Alignment with Washery Waste line along waste ponds.Above ground, run on the southern side of the existing Washery Waste line.
Section 4975106570Western haul road crossing.Buried, sleeved, approx. 1m cover.
Section 5106534302365W Series Pond levee.Above ground, west side of the washery waste pipeline on the W pond channel levee, with road crossings as nominated.
Section 6343072683838Airport Rd.Above ground, west side of the washery waste pipeline along Airport Rd.
Section 77268733365Airport Rd crossing to L1.Buried, approx. 1m cover.
Section 873338165832L1/P4 western bank.Above ground, west side of the washery waste pipeline, ending with an underground crossing.
Section 98165169048739Flume northern end.Above ground, following the edge of the flume access road.
Section 1016904190042100Flume existing section A.Underground crossing, then above ground along the flume access road. Critical — 4.5m access width to the edge of the pipeline must be maintained.
Section 111900419104100Rubberneck Access Track crossing.Buried, approx. 1m cover.
Section 1219104202081104Flume existing section B.Above ground along the flume access road. Critical — 4.5m access width to the edge of the pipeline must be maintained.
Section 132020820700492Discharge to PM1.Downhill, above ground, cross country to the discharge point. Access track by others, ≈4.5m wide.

Battery limits — the first flange connection after the bitterns pump station (15-PP-102 discharge flange) to the discharge flange into the PM1 pond.

DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 24 of 25
Construction MethodologyBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-MTH-001
Rev 0

BAppendix B — Thermal design basis summary

A one-page summary of Section 11 for site use. The full basis, method and hold points are at Section 11.

Coefficient of expansion, α0.18 mm/m/°C (PE100; confirm against supplied pipe data)
Design temperature range5.5 °C to 47.0 °C (SOW Section 8, recorded extremes)
Tie-in reference temperature25 °C nominal
Free length between restraints150 m (earth pins, SOW Section 4.3)
Movement to accommodate per 150m594 mm expansion · 526 mm contraction
Snaking regime≈ 601 mm amplitude on a 30 m wavelength
Earth pins150 m centres above ground; omitted within 500 m of an ARV or crossing; allow ~2 m per pin
AnchorsBuried crossings, tie-ins, flanges, valves, flow meters, pump station
Corridor ruleSnake amplitude measured inward from the corridor edge. 4.5 m access maintained at the widest point on sections 10 and 12

Site rules

  1. Record ambient temperature against every joint.
  2. Joint and lay in the cooler part of the day wherever practicable.
  3. Let strings relax to ambient before final closure welds.
  4. Tie in within the approved window around 25 °C. Outside it, calculate the offset, set the snake accordingly, record it and offer it to the SBR Representative.
  5. Never let thermal thrust reach a flange, an instrument or the pump station.
  6. Check the corridor and the 4.5 m access at the snake's widest point, not its centreline.

Hold points

RefPoint
T1Thermal design approved by the SBR Representative — before mobilisation
T2Snake set-out, first 500 m — SBR witness
T3Corridor and 4.5 m access survey
T4Earth pin spacing verification
T5Final tie-in temperature — at each anchored tie-in
T6Post-installation as-laid survey
DTL (WA) Pty Ltd · Commercial-in-Confidence Contract SBS10627 · PO 182113Page 25 of 25