| Document number | DTL-PRJ0072-MTH-001 |
| Revision | 0 — Issued for Approval |
| Date | 16 July 2026 |
| Attention | Mr John Stephens — Principal's Representative |
| Contract · Purchase order | SBS10627 · PO 182113 |
| Scope of work | 23092-SOW-024rD |
| Pipelines | 560-BR-301-P1 · 355-SW-302-P1 |
| Submitted under | SOW Section 4.6 — Project Execution Plan, prior to Site mobilisation |
| Document number | DTL-PRJ0072-MTH-001 |
| Document title | Construction Methodology — Bitterns Recycling Field Piping Installation |
| Project | DTL-PRJ0072 · Bitterns Recycling Project |
| Client | Shark Bay Resources Pty Ltd (SBR) |
| Status | Issued for Approval |
| Rev | Date | Description | Originated | Checked | Approved |
|---|---|---|---|---|---|
| 0 | 16 Jul 2026 | Issued for Approval — Bitterns Recycling field piping installation, SOW 23092-SOW-024rD |
This methodology is submitted for the approval of the SBR Representative in accordance with SOW Section 4.1 and Section 4.6, prior to mobilisation to Site.
This document describes how DTL (WA) Pty Ltd (DTL, the Contractor) will execute the field piping installation for the Bitterns Recycling Project at Shark Bay Resources' Useless Loop solar salt operation.
It is submitted to the SBR Representative under SOW Section 4.6 as the methodology component of the Project Execution Plan, and incorporates the detailed plan for managing the thermal dynamics of the pipeline required by SOW Section 4.1. It is issued for approval prior to mobilisation to Site.
The document is prepared so that:
This methodology covers the installation of pipeline 560-BR-301-P1 from the F7 bitterns pump station to pond PM1, and the seawater flush supply pipeline 355-SW-302-P1, between the battery limits stated in Section 4. It excludes the items listed at SOW Section 5, which remain outside DTL's scope.
| Document | Title |
|---|---|
| 23092-SOW-024rD | Bitterns Recycling Project — Field Piping Install Scope of Work |
| SBS10627 | DTL Pipeline Construction Contract (Supply & Install), as adjusted by Annexure 1 |
| PO 182113 | Shark Bay Resources purchase order |
| 00-SPE-P-010 | SBR Piping specification |
| 00-SPE-Q-001 | SBR Construction Quality Control procedure |
| 00-SPE-C-002 | SBR Roadworks Construction specification |
| 00-SPE-G-002 | Useless Loop — Information for Contractors |
| SBR-PRO-0082 | SBR Contractor Management Procedure |
| 23092-KMZ-001rB | Pipeline route, access, laydown and turnaround constraints (Google Earth) |
| 560-BR-301-P1 | Bitterns recycling pipeline — F7 to PM1 |
| 355-SW-302-P1 | Seawater flush supply pipeline |
| AS/NZS 4130 | Polyethylene pipes for pressure applications |
| AS/NZS 4131 | Polyethylene compounds for pressure pipes and fittings |
| AS/NZS 2566.1 | Buried flexible pipelines — structural design |
| POP003 | PIPA — Polyethylene pipe butt fusion jointing |
| AS 1170.2 | Structural design actions — wind actions (Region C) |
| Term | Meaning |
|---|---|
| ARV | Air release valve |
| CoC | Certificate of conformity |
| DLP | Defects liability period |
| EH&S | Environment, health and safety |
| HDPE | High density polyethylene |
| HV | High voltage |
| ITP | Inspection and test plan |
| JHA | Job hazard analysis |
| MDR | Manufacturer's data report |
| NATA | National Association of Testing Authorities |
| PE100 | Polyethylene compound, MRS 10 MPa |
| PQR | Procedure qualification record |
| SBR | Shark Bay Resources Pty Ltd |
| SDR | Standard dimension ratio |
| SOW | Scope of work |
| SWI | Safe work instruction |
| WPS | Welding procedure specification |
SBR operates a 7,000 hectare solar salt field at Useless Loop on Heirisson Prong, approximately 900km north of Perth. Bitterns — the concentrated brine remaining after the majority of the NaCl has precipitated in the crystalliser ponds — is currently collected in the F5 and F7 ponds, where it infiltrates the aquifer below the pond basement. To reduce reliance on that seepage process and recover the remaining NaCl, the bitterns will be pumped from F7 to the first pond in the evaporative process (PM1) and recycled.
| Bitterns recycling pipeline | 560-BR-301-P1 — approximately 20,700m of DN560 co-extruded white HDPE, F7 bitterns pump station to pond PM1, across 13 sections (Appendix A) |
| Seawater flush pipeline | 355-SW-302-P1 — approximately 750m of DN355, teed from the existing seawater transfer arrangement |
| Underground crossings | Crossings 2–10 by DTL. Crossing 1 (Upper and Lower Bar Road) coordinated and completed by SBR |
| Drain points | Chainages 2810 and 8060, position and orientation as directed by the SBR Representative |
| Flow meters | Three free-issued DN350 meters at chainages 8030, 13886 and 20200, with reducers and expanders to suit |
| Actuated valve | One free-issued DN350 actuated valve near the pipeline discharge |
| Air and vacuum release | ARV and vacuum breaker offtakes along the route, as fabricated items |
The battery limits of this scope are the first flange connection after the bitterns pump station (15-PP-102 pump discharge flange) and the discharge flange into the PM1 pond. Piping at the new pump location and outside these limits is excluded (SOW Section 5).
The following are free issued by SBR (SOW Section 6). DTL offloads, receives, inspects, records and stores these materials, and reports any transit damage or shortfall to the SBR Representative on receipt.
| Material | Quantity |
|---|---|
| DN560 PE100 PN10 / SDR17, 21m lengths | 3,276 m |
| DN560 PE100 PN8 / SDR21, 21m lengths | 3,066 m |
| DN560 PE100 PN6.3 / SDR26, 21m lengths | 14,784 m |
| DN355 PE100 PN8 / SDR21, 21m lengths | 777 m |
| DN560 PE100 PN12.5 / SDR13.6 sweep bends | 6 off |
| DN355 PE100 PN10 / SDR17 sweep bend | 1 off |
| DN350 actuated valve, flow meters, manual valving, drain points, air / vacuum release valves | Per drawings |
| Diesel for mobile plant, light vehicles and generators | Free issued |
The ambient conditions below are taken from SOW Section 8 (Bureau of Meteorology averages for Denham) and form the environmental basis of this methodology, including the thermal design at Section 11.
| Parameter | Value | Bearing on the method |
|---|---|---|
| Highest recorded shade temperature | 47.0 °C | Upper bound of the thermal expansion case |
| Mean daily maximum temperature | 26.8 °C | Typical working conditions |
| Mean daily minimum temperature | 17.8 °C | Preferred jointing and tie-in window |
| Lowest recorded temperature | 5.5 °C | Lower bound of the thermal contraction case |
| Relative humidity | up to 100% | Fusion face preparation and weld protection |
| Average yearly rainfall | 223.2 mm | Trench dewatering, access trafficability |
| Maximum daily rainfall | 182.4 mm | Open excavation controls at crossings |
| Maximum operating wind speed | 23 m/s | Lifting and stringing limits; AS 1170.2 Wind Region C |
DTL is responsible for ensuring plant and components supplied are suitable for these conditions, and allows for all weather throughout the Contract period.
DTL is fully self-sufficient for the construction period. SBR plant (Franna, telehandler, EWP, forklift) and facilities (crib rooms, offices, ablutions) are not relied upon (SOW Section 4.3).
| Role | Responsibility |
|---|---|
| Contractor's Representative Mr Tyson Knight | Contractual authority for DTL under SBS10627 Schedule 1 Item 3. Point of escalation. |
| Project Manager | Delivery, programme, resourcing, SBR interface, change and variation management. |
| Site Supervisor | Day-to-day execution and crew direction. Attends the 15-minute SBR daily pre-start, weekly site meetings and any other meeting requested by SBR (SOW Section 7.9). Owns the pre-start and JHA process. |
| EH&S Advisor | EH&S management system, risk assessment, incident management, statistics for the weekly report. |
| Quality / QA | ITPs, weld register and weld mapping, traceability, MDR compilation. |
| Polywelders | Butt fusion jointing to the approved WPS. Only operators qualified for the machine and pipe class weld. |
| Plant Operators | Excavation, lifting, stringing, backfill and compaction. |
All personnel complete the SBR site induction before commencing work and meet the pre-mobilisation requirements at SOW Section 7.5, including pre-employment medicals, drug and alcohol screening, police clearance and a current tickets and qualifications matrix.
DTL is responsible for all mobilisation and demobilisation, including transport of personnel, materials and equipment, all transport and other permits, site access for personnel and deliveries, and suitable notice to the SBR Representative before mobilising and demobilising (SOW Section 4.3).
The KMZ file 23092-KMZ-001rB has been reviewed to understand access, laydown and turnaround constraints across the full pipeline length. Laydown and facility locations nominated from that review will be confirmed with the SBR Representative before mobilisation. Establishment includes:
DTL will be fully self-sufficient: site office, crib, ablutions, stores, light vehicles and all construction plant. A fuel pod will be mobilised for remote refuelling of diesel plant, vehicles and gensets. Diesel is free issued by SBR and the pod refilled at the SBR workshop fuel tank, on the basis of SBR refuelling the pod once every two days. Refuelling is governed by the Hydrocarbon Controls Procedure (Section 18).
DTL will carry out and preserve all survey set-out against the supplied drawings, and is responsible for construction being in the correct positions and to the correct levels. Set-out covers the route centreline and chainages, crossings 2–10, drain points at chainages 2810 and 8060, instrument locations at chainages 8030, 13886 and 20200, and all tie-in points.
All pipe is free issued in 21m lengths and is co-extruded white. Handling protects both the pressure wall and the white outer skin — the skin limits solar gain and is integral to the thermal behaviour assumed at Section 11.
| Activity | Control |
|---|---|
| Receipt | Each delivery inspected against the consignment. Certificates of conformity, AS/NZS 4130 compliance certificates and traceability records collected at receipt for the MDR. Transit damage or shortfall reported to the SBR Representative on receipt. |
| Unloading | Nominated unloading points along the route, using slings or padded forks. No chains, hooks or bare steel against the pipe. Exclusion zones for lifting; no personnel under suspended loads. |
| Storage | Stacked on level, cleared ground on timber bearers, restrained against rolling, stack heights limited to prevent ovality. Fittings, gaskets and 316SS hardware stored under cover. |
| Stringing | Strung along the prepared benches on the nominated side of the corridor. Pipe is not dragged. Ends capped until jointing to keep bores clean. |
| Damage | Any scoring deeper than 10% of wall thickness is cut out. Damaged lengths are quarantined, tagged and reported. |
| Access | Along sections 10 and 12, a 4.5m access width to the edge of the pipeline is maintained at all times, including during stringing and laydown. |
Jointing is by butt fusion in accordance with AS/NZS 4130, PIPA POP003 and SBR specification 00-SPE-P-010, to a qualified welding procedure specification approved before production welding begins.
HDPE has a coefficient of linear thermal expansion roughly fifteen times that of steel. A 20.7km surface-laid DN560 pipeline at Useless Loop is exposed to a recorded ambient range of 5.5 °C to 47.0 °C. Left unmanaged, the resulting movement would either displace the pipeline out of its corridor, load adjacent infrastructure, or concentrate stress at the buried-to-surface transitions and at the tie-ins.
The design therefore does not attempt to prevent thermal movement. It accommodates movement along the free-laid lengths and restrains it only where the pipeline must not move.
| Parameter | Value | Source |
|---|---|---|
| Coefficient of linear thermal expansion, α | 0.18 mm/m/°C | PE100 material property (typical range 0.15–0.20). To be confirmed against the supplied pipe's manufacturer data. |
| Highest recorded shade temperature | 47.0 °C | SOW Section 8 |
| Lowest recorded temperature | 5.5 °C | SOW Section 8 |
| Nominal tie-in / restraint reference temperature | 25.0 °C | Selected within the mean daily range (17.8–26.8 °C) to balance the expansion and contraction cases |
| Design expansion case, ΔTexp | 22.0 K | 47.0 − 25.0 |
| Design contraction case, ΔTcon | 19.5 K | 25.0 − 5.5 |
| Free length between restraints, L | 150 m | Earth pin spacing, SOW Section 4.3 |
| Pipe outer skin | Co-extruded white | SOW Section 4.1 — limits solar gain and therefore peak wall temperature |
The white co-extruded outer skin is not cosmetic. It materially reduces solar absorption and so caps the peak wall temperature above ambient. The skin is protected throughout handling and installation (Section 9) because the thermal case assumed here depends on it.
| Case | ΔT | Movement per 150m |
|---|---|---|
| Expansion — tie-in at 25 °C to 47 °C | 22.0 K | 594 mm |
| Contraction — tie-in at 25 °C to 5.5 °C | 19.5 K | 526 mm |
Approximately 594mm of expansion and 526mm of contraction must be accommodated within every 150m of above-ground pipeline. This is the governing number for the method that follows.
If a length were fully restrained against the expansion case, the end thrust would be:
DN560 SDR26 (thinnest wall, longest run): wall t = 21.5 mm, Awall = 36,435 mm², ΔT = 22.0 K
| Modulus case | E | Thrust |
|---|---|---|
| Short term (rapid temperature swing) | 800 MPa | ≈ 115 kN |
| Long term (sustained, creep-relaxed) | 200 MPa | ≈ 29 kN |
Restraining the line against that thrust across 20.7km is neither practical nor desirable. The method below instead lets the pipe move where movement is harmless, and anchors it only at the points where it must not.
Above-ground pipe is laid in a deliberate serpentine within the prepared corridor rather than straight. The snake absorbs axial movement as small lateral deflection, so the pipe breathes along its own length instead of pushing at its ends.
For a serpentine of wavelength λ absorbing thermal strain α·ΔT = 3.96 × 10-3:
| Snaking wavelength λ | Required amplitude A |
|---|---|
| 30 m | ≈ 0.60 m |
| 40 m | ≈ 0.80 m |
A snake of approximately 601mm amplitude on a 30m wavelength accommodates the full expansion case within the corridor. Amplitude is set so the pipeline stays within its corridor at all times and, on sections 10 and 12, so the 4.5m access width to the edge of the pipeline is maintained at the snake's widest point — the amplitude is measured from the corridor edge inward, not from the centreline outward.
| Location | Treatment |
|---|---|
| Above ground, free running | Earth pinned at 150m centres, allowing approximately 2m per earth pin (SOW Section 4.3). Pins guide the line and hold the corridor; they do not act as full anchors. |
| Within 500m of an ARV or an underground crossing | Not earth pinned — the ARV or crossing already constrains the line (SOW Section 4.3). |
| Buried crossings 2–10 | Soil restraint and a stable ground temperature effectively fix the pipe. These are the true anchor points. |
| Buried-to-surface transitions | The critical detail. Thermal movement from the free length concentrates here. Approach lengths either side of each crossing are laid with additional snaking so movement is absorbed before it reaches the fixed point. |
| Tie-ins, flanges, valves, flow meters | Anchored. Thermal load is not permitted to reach a flange, an instrument or the pump station. Approach lengths are snaked and restrained so the connection sees no axial thermal thrust. |
| Discharge to PM1 (section 13) | Downhill and cross country. Restraint accounts for thermal movement acting with gravity on the grade. |
| Ref | Hold / witness point | Verification |
|---|---|---|
| T1 | Thermal design approval | This section approved by the SBR Representative prior to mobilisation (SOW Section 4.1). Hold point. |
| T2 | Snake set-out, first 500m | Amplitude and wavelength surveyed against Section 11.5(a) and offered for SBR witness before the regime is rolled out across the route. |
| T3 | Corridor and access check | Snaked line surveyed against the corridor; 4.5m access confirmed at the widest point on sections 10 and 12. |
| T4 | Earth pin installation | Pin spacing and the 500m ARV/crossing exclusion verified and recorded against chainage. |
| T5 | Final tie-in temperature | Ambient at closure recorded against the approved window. Hold point at each anchored tie-in. |
| T6 | Post-installation survey | As-laid position surveyed and issued, establishing the datum against which in-service movement can be checked during the DLP. |
The majority of the route runs above ground on benches and clearings prepared by others along existing access roads and flow channels. DTL lays the strung and fused pipe into the prepared corridor to the snaking regime at Section 11.5.
DTL constructs crossings 2–10, including all excavation, backfill and compaction. Crossing 1 (Upper and Lower Bar Road) is coordinated and completed by SBR. All underground crossings are direct buried pipe other than crossings 1 and 2, which are sleeved.
Section 2 is the critical interface of the works. SBR trenches and backfills for the sleeved bitterns recycling pipe and the seawater flush line. The pipeline installation must align with the SBR HV shutdown, during which power to the townsite is isolated, and SBR coordinates haul road traffic control. DTL will:
| Item | Method |
|---|---|
| Drain connection points Chainages 2810 and 8060 | DTL supplies and installs all components excluding the valves. Exact location and orientation as directed by the SBR Representative. Fabricated offtakes — no welded or bolted saddles. |
| Air and vacuum release | Fabricated offtakes to the drawings. Electro-fusion branch saddles and mechanical tapping saddles are not used. ARVs act as line constraints and are excluded from the 150m pinning regime within 500m (Section 11.5(b)). |
| Flow meters Chainages 8030, 13886, 20200 | Three free-issued DN350 meters installed for leak detection, with reducers and expanders to suit the DN560 line. Concrete mounting plinths free issued. Anchored — no thermal thrust is permitted to reach the instrument. |
| Actuated valve | Free-issued DN350 actuated valve installed near the pipeline discharge to the drawings, on the free-issued plinth. Anchored as above. Electrical and control connection is excluded (SOW Section 5). |
| Seawater flush line 355-SW-302-P1 | Teed from the existing seawater transfer arrangement to provide flush to the new bitterns pipeline, per the drawings. |
| Isolation | Isolating sleeves and washers at every location where 316SS bolting interfaces with a cast iron valve or instrument body. Stainless is not electrically connected to carbon steel. |
All testing is to the relevant regulations, standards, codes, drawings and SBR technical specifications. Where a conflict exists between these documents, DTL will seek clarification from the SBR Representative rather than proceed on an assumption.
DTL compiles a Manufacturer's Data Report for the works in accordance with 00-SPE-Q-001 during the works, for submission to SBR within two weeks of Completion. The MDR includes, at a minimum:
Records are compiled progressively rather than reconstructed at the end, so that traceability is continuous and the MDR is deliverable within the two-week window.
DTL's EH&S Management System specific to this project is submitted as part of the Project Execution Plan (SOW Section 4.6) and includes the Hydrocarbon Controls Procedure and an Emergency Management Procedure.
| Element | Application |
|---|---|
| Risk assessment | A Construction Risk Assessment Workshop is held before mobilisation. The resulting risk register is issued with the Project Execution Plan (SOW Section 7.6). |
| Task level | JHAs, safe work instructions and Take 5s for each activity. Reviewed when the task, crew or conditions change — not signed once and filed. |
| Daily pre-start | DTL's supervisor attends the 15-minute SBR daily pre-start. DTL holds its own crew pre-start against the day's JHAs. |
| Inductions | All personnel complete the SBR site induction before commencing work. |
| Fitness for work | Pre-employment medicals, drug and alcohol screening and police clearance for every person, before Site (SOW Section 7.5). |
| Principal hazards | Lifting and suspended loads; excavation and ground disturbance; live plant and traffic interface; HV shutdown at section 2; heat and hydration; remote work and emergency response distance; manual handling of 21m pipe lengths. |
| Reporting | EH&S issues and statistics reported in the weekly report to SBR. |
A traffic management plan for the works is issued with the Project Execution Plan (SOW Section 4.6).
On Completion of the works, and once demobilisation has been approved by SBR, DTL returns all areas used to their previous state. At a minimum, areas are left as they were found, with all rubbish, redundant materials and the like cleaned up and removed, to SBR's satisfaction.
Pipeline 560-BR-301-P1, F7 bitterns pump station to pond PM1, per SOW Table 1. The supplied drawings govern; this schedule is the construction sequence reference.
| Section | Ch. from | Ch. to | Length (m) | Description | Install scope |
|---|---|---|---|---|---|
| 15-PP-102 | 0 | 0 | 0 | Pump discharge flange. | Field piping scope battery limit. |
| Section 1 | 0 | 600 | 600 | 15-PP-102 to Lower Bar Rd. | First ≈200m above ground, then buried with approx. 1m cover before the bend and for the remainder along the F6/F8 pond levee road. SBR to trench and backfill. Final sleeved crossing in front of the F6/F8 culvert leads into the Lower and Upper Bar Rd crossing. |
| Section 2 | 600 | 750 | 150 | Upper/Lower Bar crossing. | SBR to trench and backfill, sleeved. Works must align with the SBR HV shutdown — power to the townsite is isolated. SBR coordinates haul road traffic control. |
| Section 3 | 750 | 975 | 225 | Alignment with Washery Waste line along waste ponds. | Above ground, run on the southern side of the existing Washery Waste line. |
| Section 4 | 975 | 1065 | 70 | Western haul road crossing. | Buried, sleeved, approx. 1m cover. |
| Section 5 | 1065 | 3430 | 2365 | W Series Pond levee. | Above ground, west side of the washery waste pipeline on the W pond channel levee, with road crossings as nominated. |
| Section 6 | 3430 | 7268 | 3838 | Airport Rd. | Above ground, west side of the washery waste pipeline along Airport Rd. |
| Section 7 | 7268 | 7333 | 65 | Airport Rd crossing to L1. | Buried, approx. 1m cover. |
| Section 8 | 7333 | 8165 | 832 | L1/P4 western bank. | Above ground, west side of the washery waste pipeline, ending with an underground crossing. |
| Section 9 | 8165 | 16904 | 8739 | Flume northern end. | Above ground, following the edge of the flume access road. |
| Section 10 | 16904 | 19004 | 2100 | Flume existing section A. | Underground crossing, then above ground along the flume access road. Critical — 4.5m access width to the edge of the pipeline must be maintained. |
| Section 11 | 19004 | 19104 | 100 | Rubberneck Access Track crossing. | Buried, approx. 1m cover. |
| Section 12 | 19104 | 20208 | 1104 | Flume existing section B. | Above ground along the flume access road. Critical — 4.5m access width to the edge of the pipeline must be maintained. |
| Section 13 | 20208 | 20700 | 492 | Discharge to PM1. | Downhill, above ground, cross country to the discharge point. Access track by others, ≈4.5m wide. |
Battery limits — the first flange connection after the bitterns pump station (15-PP-102 discharge flange) to the discharge flange into the PM1 pond.
A one-page summary of Section 11 for site use. The full basis, method and hold points are at Section 11.
| Coefficient of expansion, α | 0.18 mm/m/°C (PE100; confirm against supplied pipe data) |
| Design temperature range | 5.5 °C to 47.0 °C (SOW Section 8, recorded extremes) |
| Tie-in reference temperature | 25 °C nominal |
| Free length between restraints | 150 m (earth pins, SOW Section 4.3) |
| Movement to accommodate per 150m | 594 mm expansion · 526 mm contraction |
| Snaking regime | ≈ 601 mm amplitude on a 30 m wavelength |
| Earth pins | 150 m centres above ground; omitted within 500 m of an ARV or crossing; allow ~2 m per pin |
| Anchors | Buried crossings, tie-ins, flanges, valves, flow meters, pump station |
| Corridor rule | Snake amplitude measured inward from the corridor edge. 4.5 m access maintained at the widest point on sections 10 and 12 |
| Ref | Point |
|---|---|
| T1 | Thermal design approved by the SBR Representative — before mobilisation |
| T2 | Snake set-out, first 500 m — SBR witness |
| T3 | Corridor and 4.5 m access survey |
| T4 | Earth pin spacing verification |
| T5 | Final tie-in temperature — at each anchored tie-in |
| T6 | Post-installation as-laid survey |